Smart Charging
Using software to decide when, where, and how fast an electric vehicle should charge.
Two ways to deliver the same overnight energy
Imagine a parked vehicle that needs 12 kWh at the charger before morning. It can remain plugged in for four hours. Ignore losses for this scheduling example.
Charge earlier
Charging at 6 kW for two hours delivers 12 kWh. Other equipment may also draw heavily in those first two hours.
Spread the load
Charging at 3 kW for four hours also delivers 12 kWh. It lowers this vehicle’s contribution to the site peak if those four hours fit the departure plan.
The deadline is part of the problem
A schedule that looks attractive on a tariff chart can fail if the driver leaves early or the charger is shared. State the latest departure, energy required, site limit, and available connection time. Actual battery energy can differ from the energy metered at the charger.
How It Works
A smart-charging system typically combines charger status, battery condition, target departure times, tariffs, site constraints, and live power data. It may delay charging, reduce charging rate, share power across multiple vehicles, or prioritize certain vehicles first. In more advanced setups, it also coordinates with the battery management system so the vehicle's health limits and readiness goals stay aligned.
Follow the idea
Vehicle-to-grid introduces power export as a separate capability.
Battery Management System (BMS) · Battery management system explains why a vehicle may accept less power than a charger offers.
Related concepts
Related Yenra articles
Source · Federal Energy Management Program on managed and bidirectional charging
Return to Smart Charging in the A–Z glossary